Infra Update – October 2015
— October 30, 2015
32
ELCITA Infra Update OCTOBER:
Completed
- Underground Drainage System Survey – Completed.
- 20 feet deep well Rainwater Harvesting Pit at Various locations – Completed.
- Installation of 4 more e-Toilets – Completed.
- Construction of 1Lakh Lit Capacity Rain water harvesting tank – Completed.
- Road Maintenance work – Completed
In progress
- WIPRO junction improvement: Shifting of RMU’s under progress. (Phase 1)
- Works on a) Tessolve Road (Phase 2), b) WIPRO/Neeladri Road (Phase 2)
- MSME Road (Phase 1)
- 300 KLD Conventional STP at Konappana Agrahara Village in West Phase
- Y Junction Curve Improvement (Phase 1)
- RCC drain work @ KFC (Phase 1)
- RCC drain with cow trab for Entry gate work @ IITB (Phase 1)
- Drain work @ KSSIDC Complex (Phase 1)
Tender published
-
Providing UGD System to connect 300KLD STP, Electronics City Phase 1, Bangalore – 560 100.
-
Finalising Technology, Design, Establishment and Commissioning of 400 KLD Sewage Treatment Plant at Electronics City, Including Operation and Maintenance of the Treatment Plant for a Period of ONE (1) year.
-
Finalising Technology, Design, Establishment and Commissioning of 1 MLD Capacity Sewage Treatment Plant at Electronics City, Including Operation and Maintenance of the Treatment Plant for a Period of ONE (1) year.
Contracts Awarded
•Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs
•Quasitum Road
•Bhavani Industries Road
•Providing and laying of Asphalting using 60/70 grade bitumen from
•C-DOT to D-Mart Road Junction
•Wipro Avenue 4th cross to Wipro Avenue 5th cross road via Y-junction
•Wipro gate 5 to Wipro gate 6
•Haritha IT/Fire Station Road
Contracts Anvil
•Providing and laying of Asphalting using 60/70 grade bitumen from
•Fire station to Canara bank road Junction
•
•Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along
•TCS Road
•Fire Station to Canara Bank Junction
•Radel Industries Road
Download (PPTX, 6.62MB)