Infra Update – April 2018
— June 6, 2018
0
Download (PPTX, 8.2MB)
Completed
- Construction of RCC drain, relaying pavers and kerbstone along West Avenue 11 (Cyient Road), Electronics City, Bangalore 560100
- UPS installation at SBI road, Y Junction and Tech Mahindra Road
- Modified street light pole fixing work along West Avenue 9 (RS Jn to Petrol Bunk Jn)
- Supply & fixing shed at SWM Facility for reject waste collection
Work In Progress
- Footover bridge – Civil Work Completed & Fabrication Work in Progress
- Supply & fixing chain-link fencing at East Phase
- Construction of footpath by using the square pavers including construction of concrete drain from BHEL Junction to Wipro Junction on both sides, along West Avenue 6, West Phase, Electronics City 560100
- Construction of footpath by using the square pavers including construction of concrete drain from Cafe Corner Jn to Paramount Jn, West Phase, Electronics City 560100
- Construction of RCC pedestal work along West Avenue 6 & 9
- Shifting of pole, erecting of spun pole, relocation of transformer & raising of transformer by installing new spun pole for junction improvements at 3M & BHEL side, Electronics City, West Phase, Bangalore – 560100 – 14 Nos of cameras installed and configuration work in progress (West Avenue 8)
- Replacing existing 6-way old type MEI make conventional type RMU by 6-way compact type Schneider RMU DAS specification for F-5 feeder emanating from Keonics Muss near M/s BHEL Ltd, Electronics City, West Phase, Bangalore – 560100
Tenders
- Infrastructure works:
- Construction of footpath along West Avenue 5
- Construction of RCC culvert, Electronics City West & East Phase
- Communication related:
- Media and communication management
- Smart City:
- Laying of OFC 48F for Ring 2 & 3
- Command center S/W platform