Infra Update – February 2020

0 0

Download (PDF, 3.36MB)

Estate Management 

  • Asphalting of roads 
  • Completed at West Avenue-10 and fire station road 
  • Total length of re-surfaced road – 550m 
  • MS railing on footpath 
  • Under progress at West Lane 10, (Teknic Road) 
  • 95m completed 

Tenders 

  • Providing and applying thermoplastic paint and installation of moulded shank for road hump, stop line, pedestrian crossing and stop marking in East Phase and West Phase of Electronics City 
  • Restoration of road and footpath for 66KV KPTCL cable laid portion in East Avenue 5 from Malgudi muss station to TESCOM, East Phase, Electronics City 
  • Restoration of road and footpath for 66KV KPTCL cable laid portion in East Avenue 5 from Malgudi muss station to TESCOM, East Phase, Electronics City 
  • Restoration of road and footpath for 66KV KPTCL cable laid portion in East Avenue 5 from Malgudi muss station to TESCOM, East Phase, Electronics City 

Sustainability 

  • PMC finalized – Tide Technocrats 
  • Clearing of debris Clearing at KIDAB Land 
  • Sustainable menstruation training – Women’s Day 
  • SWM facility visit from Inventure Academy 
  • Nursery and cutlery bank 