Infra Update – January 2016

0 41

Download (PPTX, 2.88MB)

ELCITA Infra Update January:

Completed

  • Improvement work – Bus stop for BMTC below fly over – Completed (Phase 1)
  • Providing & laying Kerbstone from Tescom to Veerasandra Village Road (Phase 2)
  • Providing and laying of Asphalting using 60/70 grade bitumen
      • From Haritha IT to Fire Station Road (Phase 1)
      • From Wipro Avenue 4th cross to Wipro Avenue 5th cross road via Y-junction (Phase 1)
      • Below Fly over (Phase 1)
      • From Tescom to Veerasandra Village Road (Phase 2)
  • Road Maintenance work – Pot hole filling at various location Electronics City (Phase 1)
  • Tree root rermoving all round Infosys Hirandhani Building
  • Construction of Compound wall for 300KLD STP (phase 1)
  • Breaking the concrete foundation base along Wipro Neeladri road (Phase 1)
  • Construction of 20 feet deep well Rainwater Harvesting Pit at Various locations – Completed.(Phase 1 & Phase 2)
  • 12  E-Toilet Installed  – Completed  (Phase 1 & Phase 2)

In progress

  • Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs
    • From Wipro Gate 5 to Wipro Gate 16 (Phase 1)
    • From C-DOT to DMart Road Junction. (Phase 1)
    • Along Svenska (Phase 1)
    • Along Cyient (Phase 1)
    • Along Bhavani Industries Road. (Phase 2)
    • Along Quasitum Road. (Phase 2)
    • From Tessolve to Edizi Tools.  (Phase 2)
    • Design, Execution and Construction of 300KLD Conventional STP in Plot No. 3 (P) in ELCIA land. (Phase 1)
    • Property Inventory, Asset Management and Development of Web-based GIS Application Software for e-Governance and Management of Electronic City Industrial Township Authority (ELCITA), Bangalore.  (Phase 1 & Phase 2)
    • Supply & Erection of Steel shed for E-Waste center at SWM facility.
    • Construction of foundation with MS fencing for Relocated RMU at Wipro Gate No 15. (Phase 1)
    • Extension of  Existing column to raise the gate at the new drain level at Wipro Gate No 15. (Phase 1)
    • Improvement of road geometry at WIPRO junction
      • Drawings are approved by WIPRO and vendor finalization for Construction of compound wall in progress.

Tender published

  • Providing and laying of Asphalting using 60/70 grade bitumen Electronics City Phase 2, Bangalore – 560 100.
      • From Wipro Gate 5 to Wipro Gate 16

Contracts Awarded

  • Skywalk
    • Contract Awarded to M/s mayaPRAXIS to provide Architectural & Structural feasibility report of Skywalk system for Electronics city phase 1.
    • Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs
      • From Fire station to Canara bank road (Phase 1)
      • Providing and laying of Asphalting using 60/70 grade bitumen from
        • From C-DOT to D-Mart Road Junction
        • From Tessolve to Edizi Tools Road

Contracts Anvil

  • Proposed Concrete Road along Doddanagamangala Village – Approval awaited
  • Providing and laying of Asphalting using 60/70 grade bitumen from
    • HP Avenue
  • Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along
    • TCS Road