Infra Update – July 2017
— August 10, 2017
1
Download (PPTX, 3.92MB)
Completed:
- Footpath & Drain work– West Lane 12 (Arvind Mills Road)
- Construction of RCC Road at Pump house.
- Construction of 7KLD STP ESBR Technology at ELCITA office.
- Providing MS Railing for pedestrian safety near NTTF – West Avenue 1 (Infosys Avenue)
- 20 e-toilets Installed at various location of Electronics City and Operational– Completed. (West & East Phase)
- Shiting & Refixing the Kerstone, Removing of Pavers for Road Widening. (West Avenue 6).
- Pot Hole Filling all over Electronic City.
- Speed Humps & Traffic Arrow Marking (West Phase).
- Kerbstone Painting along West Avenue 4 & 8.
- Shifting of Pole, Erecting of Spun Pole, Relocation of Transformer, RMU & Raising of Transformer by installing new Spun Pole for Junction Improvements along West Avenue 8 (Pump house road), Electronics City West Phase, Bangalore – 560100.
Work In Progress:
- Asphalting – Pump house Road (West Avenue 8).
- Footpath Work from BHEL to 3 M Junction.
- Supply, Installation & Commissioning of Compact RMU 2nos With DAS specification & providing UG cable replacing all the BESCOM poles from Tata power to Devon Innovation, West Avenue 8, Electronics City West Phase, Bangalore – 560 100.
- Modification of existing street light poles with LED lights, Splitters, Camera, Advertisement Board, etc., (West Avenue 2)
- Providing Chamber of size 500mm x 500mm x 1000mm deep for camera located at street light pole (West Avenue 2)
- Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs from Xime Junction to Tata power rear gate & TCS Gate no 2 to Edizi Tools junction (East Avenue 2 & 4), East Phase
- RCC drain & Footpath work from Paramount to Wipro Gate no 5
- Construction of Retaining Wall & Laying of Pavers along HP Avenue (West Avenue 5).
- Shiting & Refixing the Kerstone, Removing of Pavers for Road Widening along Velankani Avenue (West Avenue 2).
- Ms Railing for Pedestrian near NTTF (West Phase).
Contract Awarded:
- Providing and laying of Asphalting using 60/70 grade bitumen
from Edizi Tools to TCS gate no 3 via Y-Junction, (East Avenue 1& 4). East Phase
Tender Published:
- Replacing Existing 6 Way old type MEI make conventional type RMU by 6 Way Compact type Schneider RMU DAS specification for F-5 Feeder Eminating from Keonics Muss near M/s BHEL Ltd, Electronics City West Phase, Bangalore – 560100.
- Providing and Laying Asphalting 60 70 grade bitumen from 3m Junction to Petrol Bunk Junction, West Lane 6 and West Avenue 9, Electronics City West Phase, Bangalore 560 100.
- Providing & Laying Asphalting 60 70 grade bitumen along West Lane 7, 8,9 and 10, West Avenue 11 Electronics City West Phase, Bangalore 560 100.
- Providing & Laying Asphalting 60 70 grade bitumen from Konar to KPTCL, West Avenue 3 and 5 Electronics City West Phase, Bangalore 560 100.
- Providing & Laying Asphalting 60 70 grade bitumen along East Avenue 5 Electronics City West Phase, Bangalore 560 100.
Contracts on Anvil
- Providing House Keeping Services to ELCITA within e-city Industrial Township Area.
- Providing Services for Solid Waste Management to ELCITA within e-city Industrial Township Area.
- Shifting of Pole, Erecting of Spun Pole, Relocation of Transformer & Raising of Transformer by installing new Spun Pole for Junction Improvements at 3m & BHEL Side, Electronics City West Phase, Bangalore – 560100.
- Construction of 400 KLD STP in KSSIDC Land, West Phase.
- Construction of 500 KLD STP in KIADB Land, East Phase.