Infra Update – June 2017

0 0

Completed:

  1. Providing MS Railing for pedestrian safety – West Avenue 1 (Infosys Avenue)
  2. Construction of RCC Culvert 5th Cross junction – West Avenue 8
  3. Footpath & Drain Works along West Avenue-8 (Police Station Side)
  4. Construction of RCC Drain Footpath works near Siemens – West Avenue 1
  5. Footpath & Drain Works along West Avenue-9 (Petrol Bunk Road)
  6. 20 e-toilets Installed at various location of Electronics City and Operational– Completed.  (West & East Phase)

In progress:

  1. Shifting of Pole, Erecting of Spun Pole, Relocation of Transformer, RMU & Raising of Transformer by installing new Spun Pole for Junction Improvements along West Avenue 8 (Pump house road), Electronics City West Phase, Bangalore – 560100.
  2. Modification of existing street light poles with LED lights, Splitters, Camera, Advertisement Board, etc.,
  3. Supply, Installation & Commissioning of Compact RMU 2nos With DAS specification & providing UG cable replacing all the BESCOM poles from Tata power to Devon Innovation, West Avenue 8, Electronics City West Phase, Bangalore – 560 100.
  4. Construction of RCC Road at Pump house.
  5. Proposed Skywalk from Ecity West phase to East Phase.
  6. Supply & Laying 6 inch PVC pipe laying for Street light pole, East Avenue 1
  7. Providing Chamber of size 500mm x 500mm x 1000mm deep for camera located at street light pole
    1. West Avenue 8 & 6
    1. West Avenue 2
  8. Construction of RCC Culvert opp BARON Electronics – West Avenue 8
  9. Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs from Xime Junction to Tata power rear gate &  TCS Gate no 2 to Edizi Tools junction (East Avenue 2 & 4), East Phase
  10. RCC drain & Footpath work from Paramount to Wipro Gate no 5
  11. Footpath work along HP Avenue.
  12. Drain work– West Lane 12 (Arvind Mills Road)
  13. Construction of 3KL Capacity UG Sump for E- Toilet
    1. Y junction East phase
  14. Construction of 7KLD STP ESBR Technology at ELCITA office
  15. Construction of RCC drain (XIME)– East Avenue 2

Contract Awarded

  1. Providing and laying of Asphalting using 60/70 grade bitumen
  1. from Edizi Tools to TCS gate no 3 via Y-Junction, (East Avenue 1& 4). East Phase
  2. Along Café Corner & JP IT Park Road

Contracts on Anvil

  1. Providing House Keeping Services to ELCITA within e-city Industrial Township Area.
  2. Replacing the Existing RMU with New Compact RMU near M/s BHEL Ltd.
  3. Construction of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs
    1. Erkadi System to Arvind Mills (West Phase)
  4. Construction of 400 KLD STP in KSSIDC Land, West Phase.
  5. Construction of 500 KLD STP in KIADB Land, East Phase.