Estate Management
- Asphalt Work at East Avenue 3 (Tech Mahindra Road)
- Drain and footpath work at West Avenue -2 (Velankani jn to SJR Equinox)
- Railing work at West Avenue 6 (Wipro jn to Shikaripalya)
- Drain and Footpath work at West Avenue 11(KSSIDC)
- Drain and footpath work at West Avenue -2 (SJR Equinox to HP Surya Wave)
- Drain and Footpath Work at West Avenue 3 (Oterra Junction to KPTCL)
- Drain and Footpath work at West Lane 8 (Teknic to Syscon Junction)
- The Smart 120 Watts LED Lights -145 No’s Installation completed
Tenders
- Painting of kerbstones and median with one coat of primer and two coats of enamel paint along roads in East Phase of Electronics City, Bangalore 560 100.
- Supply and fixing of MS Railing on Footpath in West Avenue 10 (From Gollahalli Junction to Fire Station Junction), West Phase, Electronics city, Bangalore-560100.
- Supply and fixing of MS Railing on Footpath in West Avenue 9 From RS Junction to Petrol Bunk Junction (Interplex Side), West Phase, Electronics city, Bangalore-560100.
- Supply and fixing of MS Railing on Footpath in West Avenue 9 From RS Junction to Petrol Bunk Junction (Interplex Side), West Phase, Electronics city, Bangalore-560100.
Sustainability
- Supply, Installation and commissioning of Baling machine for ELCITA SWM facility.
- Dismantling of greenhouse under progress
- Waste segregation training at Titan