Infra Update – May 2016
— May 23, 2016
26
Download (PPTX, 6.46MB)
Completed
- Providing and laying of Asphalting using 60/70 grade bitumen along Bhavani Industries & Quasitum Road (Phase 2)
- Construction of 20 feet deep well Rainwater Harvesting Pit 38 Nos at Various locations – Completed.(Phase 1 & Phase 2)
- 15 e-toilets Installed at various location of Electronics City and Operational– Completed. (Phase 1 & Phase 2)
- Supply & Erection of Shed for Organic waste processing plant & Shredding plant at KIADB Land – Completed. (Phase 2)
- Providing & Laying WMM Road from MSME Building to Exit Gate. (Phase 1)
- Laying Cover Slab at BESCOM (Phase 1)
- Drain Work along Gollahalli Road (Phase 1)
- RMU Yard work at Wipro Gate no 5 (Phase 1)
- Drain Cleaning Work at Various location (Phase 1 & Phase 2)
- Cross Drainage work at Gollahalli Junction (Phase 1)
- Construction of Drain work adjacent to RajKamal Industries
- Construction of Drain, Pavers & Cover slab Adjacent to RajKamal Industries (Phase 1)
- Construction of Drain, Cover slabs along HP Avenue Road. (Phase 1)
- Construction of SSM Drain work in front of BETL (Phase 1)
- Construction of Footpath & Ramp work in front of KFC (Phase 1)
- Providing & Laying Sewer line, from Doddangamangala village manhole to lake Electronics City. (Phase 2)
- Construction of Drain from JJ glastronics to existing drain (Phase 1)
- Supply & Erection of Shed for Organic waste processing plant & Shredding Area at KIADB Land. (Phase 2)
- Construction of Compound Wall at Wipro Gate No 5 (Phase 1)
- Construction of Compound Wall at Wipro Gate No 12 A (Phase 1)
In progress
- — M/s mayaPRAXIS had submitted the Draft preliminary feasibility Report on Skywalk system, Electronics city phase 1 for approval.
- Re Fixing of Kerbstone and providing pavers along Velankani Road. (Phase 1)
- Re fixing Drain cover slab in front of Lord Plaza. (Phase 1)
- Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs
- From Wipro Gate 5 to Wipro Gate 16 (Phase 1)
- From C-DOT to DMart Road Junction. (Phase 1)
- Adjacent to KSSIDC Compound wall (Phase 1)
- In front of Lemon Tree Hotel (Phase 1)
- Canara bank fire station junction (Phase 1)
- Along HP Avenue Road
- Providing and laying of Asphalting using 60/70 grade bitumen From Wipro Gate 5 to Wipro Gate 16 (Phase 1)
- Providing and laying of Asphalting using 60/70 grade bitumen From Canarabank road/ Fire station Junction (Phase 1)
- Concrete Pavements along Doddanagamangala Village Road (Phase 2)
- Supplying & Laying Sewer Pipe line from Existing Manhole to Septic Tank located in KIADB Land. (Phase 2)
- Property Inventory, Asset Management and Development of Web-based GIS Application Software for e-Governance and Management of Electronic City Industrial Township Authority (ELCITA), Bangalore. (Phase 1 & Phase 2)
Contracts Awarded
- Providing and laying of Asphalting using 60/70 grade bitumen along
- Café Corner & JP IT Park Road
- C-DOT to D-Mart Road Junction
Contracts Anvil
- Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along
- TCS Road
- Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP.
- Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2