Infra Update – May 2020
— May 20, 2020
0
Download (PPTX, 5.42MB)
Estate Management
- Footpath and Railing work completed at East Phase Entrance.
- MS Railing work Completed at West Avenue 6 (BHEL jn to WIPRO Jn)
- Improvements of Drain and Footpath, work under progress in West Avenue 4 from Momentive to ELCIA Complex
- Restoration of Road and Footpath for 66 KV KPTCL – Work under Progress in East Avenue 5
Tenders
- Supply and fixing of MS Railing along West Avenue-8 (Paramount Jn to Flextronics), West Phase, Bangalore-560100.
Sustainability
- SOP for Covid-19 waste management created
- Diversion of used masks and gloves to Biomedical waste incinerator.
- 265 Kg disposed in the month of May
- Tide Technocrats Pvt Ltd finalized as the PMC
- Debris clearing at KIADB land started
- Environmental quiz for ELCITA staff
- Sapling Plantation at Ananth Nagar School
- Drawing /Essay competition for school students
- Sustainable smart Bus stop design contest for member companies