Completed:

  • Providing and laying of Asphalting using 60/70 grade bitumen along
    • West Avenue-7 (Wipro Neeladri Road) (West Phase).
    • West Lane-3 (JP IT Park Road) (West Phase).
    • 300 KLD STP (West Phase)
  • Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along
    • West Lane-1 (near Goa Estate) (West Phase)
    • West Avenue-9 (near Celstream) (West Phase)
    • KSSIDC Complex (West Phase)
  • Construction of RCC Drain along West Lane-6 (Ramsoft Road). (West Phase)
  • Construction of RCC Culvert in front of MSME.(West Lane-1) (West Phase)
  • Construction of RCC Culvert over storm water drain to continue the footpath near pump house (West Avenue-8). (West Phase)
  • Construction of 6KL Capacity UG water sump for STP Treated water storage at KIADB. (East Phase)
  • Providing & Fixing kerbstone for 300 KLD STP Road (West Phase)
  • Removing & raising the Existing stone Kerbstone at KSSIDC Complex. (West Phase)
  • RS Junction Improvement works. (West Phase)
  • Construction of Footpath along
    • In front of Petrol bunk existing Gate West Lane-1 (West Phase)
    • KSSIDC Complex (West Phase)
  • Construction of 20 feet deep well Rainwater Harvesting Pit 48 Nos at Various locations – Completed. (West & East Phase)
  • 16 e-toilets Installed at various location of Electronics City and Operational– Completed.  (West & East Phase)  & 2 More E- Toilet Installation Work in Progress

 In progress:

  • Providing and laying of Asphalting using 60/70 grade bitumen inside KSSIDC Complex internal Road. (West Phase).
  • Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along East Avenue-1 (TCS Road) (East Phase)
  • Construction of SSM Drain along West Avenue-5  (near Ramakrishna Hospital). (West Phase)
  • Construction of 80 KL Capacity Septic Tank (KSSIDC) & Sewer line work, West Avenue-10 (Canara bank road). (West Phase)
  • Kerbstone Painting work along West Avenue-7 (Wipro Neeladri Road). (West Phase)
  • Construction of Compound wall of 1m height above the existing Wall at KIADB land. (East Phase)
  • Laying Kerbstone for 300KLD STP Road. (West Phase)
  • Property Inventory, Asset Management and Development of Web-based GIS Application Software for e-Governance and Management of Electronic City Industrial Township Authority (ELCITA), Bangalore.  (West & East Phase)

Contracts Awarded:

  • Providing and laying of Asphalting using 60/70 grade bitumen along
    • Café Corner & JP IT Park Road
    • KSSIDC Complex Internal Roads

Tender Published:

  • Providing Security Services to ELCITA within Ecity Industrial Area.
  • Providing and laying of Asphalting using 60/70 grade bitumen from Tech Mahindra to Malgudi MUSS via Tata BP Solar, Shanthipura, Edizi & Tescom, Electronics City East Phase.
  • Construction of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs along Petrol Bunk Road & Golden Tulip Road.

 

Contracts Anvil:

  • Providing House Keeping Services to ELCITA within Ecity Industrial Area.
  • Construction of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs along XIME Road, Electronics City East Phase.
  • Landscaping work below fly over & the median located in West & East Phase.
  • Construction of 500 KLD STP in KIADB Land, Electronics City East Phase.

Leave a reply